D.E.W. Plumbing stays ahead of the curve on all new plumbing technologies and procedures. We've provided a sample of our installation process in order to demonstrate our commitment to consistency and customer satisfaction.
|
 |
Initial meeting with Builder, Homeowner, or both
Discuss any changes or additions to plans, locate all basement plumbing if not clearly marked on plans, verify plumbing stub out location, schedule installation of slab plumbing. |
 |
Installation of slab plumbing
Install all drain lines and waterlines underground to specified location, pressure test with air or water. (This process typically takes a ½ day to complete) |
 |
Installation of water and sewer line
Call UPC for locate, make sure there are no obstructions preventing work to be completed, install water and sewer line, call in inspection request, cover up after inspection. (This process typically takes 1 day to complete)
|
 |
Rough plumbing step one
Meet builder and or homeowner on jobsite, discuss location of outside hosebibbs, water heaters, fixtures ect. Confirm selections for tubs, showers and valves. |
 |
Rough plumbing step two
Install drain lines, waterpipes, tubs and all other necessary components prior to sheetrock. Pressure test drain lines and waterlines with water and or air.
|
 |
Rough plumbing step three
Walk house with a thorough 18 pt. checklist created by DEW Plumbing field supervisors to inspect certain details that could otherwise be easily overlooked. Call in for rough plumbing inspection (when applicable). Note: It is not always necessary to schedule an initial meeting and a meeting on the jobsite once we are familiar with repetitive spec house plans.
|
 |
Final plumbing
Install faucets, sinks, commodes, appliances, water heaters etc. Turn on water and test all fixtures.
|
 |
Final walk thru
Install any fixtures not able to set during final plumbing stage. Walk house with a 23 pt. checklist created by DEW Plumbing field supervisors to inspect certain details that could otherwise be easily overlooked. Make sure all fixtures are functioning properly, place indicator tags on all outside hosebibb and main shutoffs. Confirm house is ready for final plumbing inspection.
|
|
|
|
|
|
| |